Skip to main content

Table 1 Work schedule shows an example of an automatically generated work schedule listing the work for the next nine days.

From: Documentation system for plant transformation service and research

ID Date CV Step Method Selection Plasmid Id Transformation date
590 15.09.2009 MM Hand over Tomatotransformation_Blau Hyg 312121 17.06.2009
628 16.09.2009 IPA-6 Transfer Shoot induction Tomatotransformation_IPA6 Km 167 19.08.2009
618 16.09.2009 PH Transfer Shoot induction Tobaccotransformation Kanamycin Km 309084 28.07.2009
617 16.09.2009 SNN Exchange medium Tobaccotransformation Hygromycin Hyg 314778 28.07.2009
619 18.09.2009 MM Transfer Shoot induction Tomatotransformation_Blau Hyg 312853 29.07.2009
614 18.09.2009 MM Transfer Shoot induction Tomatotransformation_Blau Hyg 312852 29.07.2009
635 20.09.2009 MM Transfer Shoot induction Tomatotransformation_Blau Hyg 312121 14.08.2009
634 20.09.2009 MM Transfer Shoot induction Tomatotransformation_Blau Km 305498 14.08.2009
633 23.09.2009 SNN Transfer Shoot induction Tobaccotransformation Hygromycin Hyg 315635 14.08.2009
643 24.09.2009 PH Transfer Shoot induction Tobaccotransformation Hygromycin Hyg 315285 04.09.2009
  1. (ID = Experiment identifier, CV Cultivar)